EPE Foam Machine production process
1, feeding, mixing: through the feeding system will be quantitative cement, foam agent, foam stabilizer added to the mixer, dry mix for 30 seconds;
2, stirring: the amount of warm water will be added to the mixer, wet stirring for 2 minutes; the amount of the blowing agent into the mixer stirring 8-15 seconds;
3, injection molding, foaming: the slurry will be injected into the mold foam, foaming process about 3-5 minutes;
4, the initial conservation: After the completion of injection molding for several hours to carry out the initial maintenance;
5, stripping: foaming cement insulation board to complete the initial coagulation, with the initial strength can be stripping;
6, cutting: with a certain strength of the foam insulation board insulation mold can be cut off after cutting, cutting specifications according to the need to adjust the cutting blade;
7, polyureth